Oxygen pipe skimming construction programme

    News

Check category

Oxygen pipe skimming construction programme

Oxygen pipe skimming construction programme

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2015-05-22 11:06
  • Views:
icon icon icon icon

(Summary description)Oxygen Pipe Skimming Construction Program Agency:Audit:Approval:Safety:Project Manager2011.9.1 Table of Contents1 Memorandum 11 of 2 Foundation3 Construction Preparation14 General Provisions for Cleaning and Skimming15 Skimming Method26 Skimming Cleaning Procedures and Requirements27 Testing3 of Fat Portion8 Construction Measures33 Safety and Environmental Measures910 Cleanliness Inspection Record Form4 1 Preparation Instructions1.1. only.

Oxygen pipe skimming construction programme

(Summary description)Oxygen Pipe Skimming Construction Program Agency:Audit:Approval:Safety:Project Manager2011.9.1 Table of Contents1 Memorandum 11 of 2 Foundation3 Construction Preparation14 General Provisions for Cleaning and Skimming15 Skimming Method26 Skimming Cleaning Procedures and Requirements27 Testing3 of Fat Portion8 Construction Measures33 Safety and Environmental Measures910 Cleanliness Inspection Record Form4 1 Preparation Instructions1.1. only.

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2015-05-22 11:06
  • Views:
Information

Oxygen pipe skimming construction programme

Agency.

Audit.

Ratification.

Security.

Engineering Project Manager

2011.9.1

Table of contents

1 memo 1

1 of 2 basis

3 Construction Preparation 1

4 General provisions for cleaning and degreasing1

5 Degreasing method 2

6 Degreasing cleaning procedures and requirements2

7 Fat part of test 3

8 Construction Measure 3

3 Safety and environmental protection measures9

10 Cleanliness inspection record sheet 4

1 Preparation note

1.1. This applies only to the construction of the XXXXXXXXXX oxygen pipe.

1.2. Assuming that the construction conditions have been prepared, the construction plan is to introduce the "three-way" to the site, steam, compressed air into the site.

1.3. The construction of the oxygen pipe is carried out in addition to the execution of the plans, which have been approved for the technical piping installation and construction.

2. Preparation of foundations

2

2.1. "Construction and Acceptance of Degreasing Project HG20202-2000"

2.2. process pipeline owner's construction drawings.

3 Construction Preparation

3

3.1. the contractor should study the procedure carefully and know how to clean and degrease the product. Before construction, safety and technical disclosure should be made to the construction workers.

3.2. take snowfall, frost shed, construction site layout, construction personnel.

3.3. prepare silk, plastic sheeting, tape, cotton consumer goods, etc.

3.4. prepare equipment for UV lights, paper, pure camphor testing.

4 General provisions for cleaning and degreasing

4

4.1. degreasing of pipes, pipe fittings, valves and other tools should be completed prior to installation.

4.2. there are obvious traces of grease on the parts. grease and dirt can be removed with kerosene before degreasing with a degreasing and skimming solution.

4.3., inspection and installation of tools, gauges, measures, etc., must be preskimmed as required. No degreaser is used. Work clothes, shoes, gloves and other protective equipment must be clean and oil free. Protective plastic sheeting should be oil-free.

4.4. After degreasing of pipes, fittings, valves, etc., they must be checked and signed by the person concerned according to the requirements of the inspection, and sealed promptly with plastic sheeting and tape to prevent contamination and debris from entering. The next process can be carried out at this point.

4.5. the person responsible for closure checks the qualified skimmed parts and adds the correct sign for storage. Whether the parts to be skimmed are qualified or non-skimmed, are stored in isolation and are phase free.

The organic solvent oil content is 4.6. it should not exceed 50mg / L. The solvent can be used as the crude oil content and then the qualifying solvent is used again. Solvents greater than 500 mg/L should be treated with oil and tested for use as a degreasing agent. The solvent can be used as a degreasing agent.

4.7 Install unfinished piping promptly, blocking the goods with plastic sheeting and tape; open again and clean the welds with acetone to prevent secondary contamination.

5 Degreasing method

5

5.1. the construction project of the oxygen piping coincides with the autumn and winter seasons, the degreaser as well as the initial plan of steam immersion in 3 to 5% sodium hydroxide (NaOH) solution heated to 80 ° C. Inconvenient pipes or valves are wiped by wiping, the carrier immersion valve swabbing method and sporadic parts wiped using acetone.

5.2. Purchased degreasers must have acceptable quality documentation and be subjected to material inspection according to the procedure.

6 Degreasing cleaning procedures and requirements

6

6.1. cleaning and degreasing procedures

6.2. cleaning and degreasing requirements

6.1.1. for piping, the resistance test method is used for pipe fittings that are submerged or wiped. For flanges, valves, gaskets, and fasteners, use the submersion method for all.

6.1.2. for inconvenient valve housings and fractional parts, use the acetone wipe method.

6.1.3. degrease the valves and then pass the test voltage, allow the valves to be removed, split into sections to remove debris, and soak in the solvent trichloroethylene for 1 to 1.5 hours. The same method is used for bolts and metal gaskets.

6.1.4. the pipe shall be degreased, prefabricated, degreased, one part of the pipe and branch openings shall be fully constructed, bevels sanded, welds shall be cleaned of slag splatter, etc., and verified by the quality inspector. Drying shall be performed with clean, dry air.

7 Testing fat parts

7

According to 7.1. standard HG202022000, parts shall be degreased using a random test method.

7.1.1. the surface shall be inspected for degreasing using ultraviolet light at a wavelength of 3200 to 3800 angstroms and passed without oil fluorescence.

7.1.2. clean and dry the white filter paper, wipe off the greasy surface and certify that the paper is free of traces of grease.

7.1.3. check steam blowing out condensation with less than 1 mm of 100% camphor to stop the rotation to qualify.

8 construction measures

8

8.1. frost fortification loss based on rain and snow on site.

8.2. introduction of 1" compressed air hose.

8.3. introduction. Low pressure steam pipe 1".

Serial number

project name

Dosage (kg)

1

gasoline

~5

2

Oil-free plastic sheeting

~40

3

adhesive tape

30 volumes

4

absorbent cotton

~15

5

silks

~5

6

pure camphor

0.25

7

1" galvanized steel pipe

30 meters

8

1" rubber hose

5 m

9 safety and environmental protection measures

9

9.1. site construction safety and technical operating procedures must be strictly implemented.

9.2. the construction site should be smooth and level, there should be fire-fighting facilities on site, and clean water should be prepared.

9.3. the clean construction site should be well ventilated, smoking, eating and playing in the field are prohibited.

9.4. personnel engaged in this work, construction should wear clean uniforms, shoes, acid and alkali gloves, protective eyewear masks, etc., construction equipment should be degreased, and have special supervision.

9.5. "Danger" and "Flammable" signs should be set up in the fertilizer field, and the construction area should be demarcated around the signs.