Group manufacturing
Quality Assurance System
Quality Assurance System
- Categories:Group Manufacturing
- Time of issue:2020-10-14 13:16:16
- Views:0
■ Quality policy and quality objectives
√ Quality Policy:
Establish systems for compliance and continuous improvement;
Safety in production, brand enhancement, and customer satisfaction.
√ Quality goals:
No major liability incidents.
■ Quality assurance system organization chart (slightly)
■The quality assurance system includes quality assurance manuals, procedure documentation (management system), work (process) documentation, records (forms, cards), etc.
■ List of control points for each quality control system in the control system. (Column: check the control points and control points of the quality control system)
serial number |
Control Links |
Control content |
||||||
names |
Form of control |
names |
Control content |
Type of control |
responsible person |
Witness information |
||
1. |
1.1 |
examine ready |
review and inspection |
Prepare and prepare inspection documents |
Testing the suitability, validity, adequacy of preparation of standards and process documents for the preparation of procedures |
R |
person responsible for inspection |
Inspection guidelines for steel pipes, welded pipes and pipe fittings |
1.2 |
Preparation of inspection forms | Control effectively meets inspection requirements and facilitates production |
R |
person responsible for inspection | inspection report | |||
1.3 |
Selection and calibration of inspection devices | The accuracy of the inspection device meets the measurement requirements and the weekly inspection of the inspection device. |
R |
Person responsible for measurement | Certificate of conformity, inspection records | |||
1.4 |
Staffing | Competencies, practical experience and assessment |
R |
person responsible for inspection | List of inspectors | |||
2. |
2.1 |
Incoming Product Inspection | Inspection and approval | Re-inspection of raw material acceptance | Quality certificate, type and size check, material physical and chemical test re-inspection |
H |
Material responsibility | Acceptance records and physical and chemical re-inspection reports of storage |
2.2 |
||||||||
3. |
3.1 |
process inspection | inspections | Material Inspection | Material, specification, size, logo |
E |
inspector | Material identification cards, inspection records |
3.2 |
heat treatment | Equipment operation, heat treatment temperature and time records |
R |
person responsible for heat treatment | Heat treatment temperature time recording | |||
|
welding | Record of equipment operation and welding parameters |
R |
Person responsible for welding | Recording of welding parameters | |||
3.3 |
Other tests | Dimensions, surface quality, marking, protection |
E |
Operators, inspectors | Process inspection report | |||
4. |
4.1 |
Factory Inspection | Approval and inspection | Size and shape | Outside diameter, wall thickness, sizing length, end profile, curvature |
E |
inspector | Inspection records |
4.2 |
surface qualities | Cracking, splitting, folding, re-skinning, over-acid washing, residual oxide skin |
E |
inspector | Inspection records | |||
4.3 |
Review of other tests | Chemical analysis, tensile test, round test, intergranular corrosion, grain size, nondestructive testing, hydrostatic test, impact test |
R |
person responsible for inspection | Test reports/records, specimens | |||
4.4 |
markers | Trademarks, names, steel numbers, specifications, standards, furnace numbers, production batch numbers, etc. |
H |
inspector | finished product | |||
4.5 |
substandard treatment | Marking, segregation, recording, reporting, evaluation, disposal and re-testing |
R |
person responsible for inspection | Non-conforming disposal reports, records | |||
4.6 |
packaging | Package identification, product protection |
H |
inspector | Final inspection records of finished products | |||
4.7 |
Factory documentation | Various acceptance slips, inspection records, physical and chemical test reports, NDT records, heat treatment, quality certificates, etc. |
H |
person responsible for inspection | Final inspection records of finished products |
Note: E - Checkpoint R - Checkpoint H - Stop Point
■Quality Control System Diagram of Quality Control System (Quality Control System Diagram)
SHANG SHANG STAINLESS STEEL PIPE Power by:www.300.cn 浙ICP备17053523号